Week of 25 Aug — 9 installs, 2 surveys and 3 commissions across 4 install crews. 85% of the diary is booked (17/20 crew-days); 3 slots idle. Two jobs can't be booked yet — both waiting on the DNO.
Dispatch desk4 crews out · 4 on the clock·Diary 85% booked · 3 slots free·2 awaiting DNOweek of 25 Aug · live board
Installs bookedthis wk
9
panel + BESS fits this week
Surveysthis wk
2
roof + G98/G99 assessments
Commissionsthis wk
3
EIC · BS EN 62446 · MCS
Crews on the roadtoday
4
4 on the clock now
Diary bookedtight
85%
17 of 20 crew-days
Needs schedulingblocked
2
blocked on G99 consent
Crew load by day
installer-days booked · capacity 4/day
85%
utilised
4
Mon 25
4
Tue 26
4
Wed 27
2
Thu 28
3
Fri 29
Amber = fully committed (no free crew). Thu & Fri hold slack for the two DNO-blocked jobs the moment consent lands.