Delivery / Job
J-1042
Aidan Kelly · 6.4kWp · 10.4kWh in Strabane — £11,240 at 38.7% margin, now at "Install". Every stage, cert, part and photo tracked in one record — nothing on a clipboard.
J-1042 · Solar + Battery · Liam B, Sean G
Aidan Kelly
6.4kWp · 10.4kWh · Strabane BT82 8DP · due Today
InstallG99 · Approved
Contract value
£11,240
0% VAT · SEG eligible
Gross margin
38.7%
Est. generation
5,720
kWh / yr est.
DNO connection
G99
DNO-G99-4471 · Approved
Job lifecycle
survey → handover · every stage stamped4/7 doneSurvey✓28 Jul
Roof survey + design sheet
Design & quote✓30 Jul
Quote accepted, 30% deposit
DNO / G99✓2 Aug
G99 approved — the DNO
Procurement✓12 Aug
PO-2231 received & checked in
InstallCurrentToday
Crew on site — day 1 of 2
Commission—
BS EN 62446 tests + EIC
MCS handover—
MCS cert + handover pack + MID
Job costing
where the money goes · live from Xero38.7% GMEquipment (panels, inverter, battery)£4,820
Consumables + mounting£640
Labour (2 installers × 2 days)£980
Scaffolding (sub-contract)£450
Direct cost£6,890
Contract £11,240£4,350 gross
cost £6,890margin 38.7%
Compliance chain
6DNO — G99 approvalSigned
the DNO · 2 Aug
EIC (BS 7671)Due
Due on commissioning
Commissioning (BS EN 62446)Due
Due tomorrow
MCS certificatePending
After commissioning
MID registrationPending
≤10 working days
RECC + handover packPending
On handover
Stock allocated
5/6 loaded16×Loaded
440W mono panel
Van — Sean G
1×Loaded
Hybrid inverter 5.0kW
Warehouse
2×Loaded
Battery module 5.2kWh
Warehouse
12×Loaded
Mounting rail (2.1m)
Van — Liam B
16×Loaded
DC optimiser
Van — Sean G
40×To load
DC cable 6mm²
Van — Liam B
Site photos
4Customer
AKAidan Kelly
C-118 · Strabane BT82 8DP
Customer wants app monitoring set up on handover. Battery bay pre-cleared.