Delivery / Job
J-1044
Bradley Farm Ltd · 12.0kWp · 20.8kWh in Garvagh — £24,900 at 37.1% margin, now at "Procurement". Every stage, cert, part and photo tracked in one record — nothing on a clipboard.
J-1044 · Solar + Battery · Sean G, Liam B
Bradley Farm Ltd
12.0kWp · 20.8kWh · Garvagh BT51 5JH · due 2 Sep
ProcurementG99 · ApprovedAt risk
Contract value
£24,900
0% VAT · SEG eligible
Gross margin
37.1%
Est. generation
11,400
kWh / yr est.
DNO connection
G99
DNO-G99-5120 · Approved
Job lifecycle
survey → handover · every stage stamped3/7 doneSurvey✓5 Aug
Barn roof survey (3-phase)
Design & quote✓9 Aug
Quote accepted, deposit paid
DNO / G99✓20 Aug
G99 approved
ProcurementCurrentIn progress
Batteries on order — PO-2252
Install—
Booked 2 Sep
Commission—
TBC
MCS handover—
TBC
Job costing
where the money goes · live from Xero37.1% GMEquipment£11,200
Consumables + mounting£1,450
Labour (2 installers × 3 days)£1,800
Scaffolding + access£1,200
Direct cost£15,650
Contract £24,900£9,250 gross
cost £15,650margin 37.1%
Compliance chain
6DNO — G99 approvalSigned
the DNO · 20 Aug
EIC (BS 7671)Pending
On commissioning
Commissioning (BS EN 62446)Pending
After install
MCS certificatePending
After commissioning
MID registrationPending
Later
RECC + handover packPending
On handover
Stock allocated
2/4 loaded30×Loaded
440W mono panel
Warehouse
2×To load
Hybrid inverter 5.0kW
Warehouse
4×To load
Battery module 5.2kWh
PO-2252 (on order)
40×Loaded
Mounting rail (2.1m)
Warehouse
Site photos
2Customer
BFBradley Farm Ltd
C-131 · Garvagh BT51 5JH
Install blocked on battery lead time — flagged on the decisions strip.